Cliff Castle Casino

Titan Power provided project management to Cliff Castle Casino located north of Phoenix to install and replace an emergency generator system. Titan Power installed three parallel 750kW generators, 2 new SES and 2 – 3000 Amp ATS. The system is intelligent and can determine the casino’s needs, and tailor the generator output to meet these needs. Titan Power Project Management Team provided a solution that reduced the project time line by two months and provided cost-savings to the casino.