Titan Power provided project management for a casino facility north of Phoenix to install and replace its emergency generator system. The project included the installation of three parallel 750 kW generators, two new SES, and two 3000 Amp ATS.
The intelligent system is designed to assess the facility’s needs and adjust generator output accordingly. Through effective planning and coordination, Titan Power’s project management team reduced the project timeline by two months while also delivering cost savings.